Line 9 of Barcelona Metro - Phases I & II

Construction of the new Metro Line 9 of Barcelona that will connect the airport of El Prat with Badalona (including tunnels and stations). Our staff has worked on various stations, the introduction wells and on the slab through certain sections with 50m depth and several kilometers long.

  • Location: Barcelona
  • Construction company: UTE Gorg L9. Acciona, Comsa, Sorigue, Dragados
  • Construction year: 2005
  • Execute items:

    2284.21 ml. Construction of the intermediary slab including the daily movement of the metalic suporting structure and positioning of reinforcing steels

    18,273.65 m3 Pumping, pouring and vibration of concrete

    11421.03 ml. Laying of PVC pipe

    18273.65 u. Perforations for the connection of the slab with segments rings

    9023.14 ml. Dismantling of ventilation ducts

    8207.15 m2 Formwork of flat surfaces

    53.5559,35 m3 Pouring and vibrating of structural concrete

    1900.00 m3 Manual excavation at surface level or between walls

    3735.02 m3 Demolition with manual or mechanical means of concrete structures

    4374.50 u. Perforation of the rings with mortar or resin

    350.00 ml. Construction of a concrete collector