Pumping Station in Sant Boi de Llobregat

On this station, our staff carried out the manholes formworks, and masonry works relating to urban development.

  • Location: Sant Boi de Llobregat (Barcelona)
  • Construction company: Acsa Sorigué
  • Construction year: 2008
  • Execute items:

    27317.12 ml. Pipe laying

    599.40 ml. Laying and anchoring of New Jersey type safety barrier

    75.20 ml. Trench leveling

    2850.00 m2 formwork of manholes, walls and slabs

    1800.00 m3 Pouring concrete in manholes, walls and slabs, including vibration and cure

    10,500.00 m3 of soil compaction in trench

    17418.47 m3 Backfillings used for the realization of the subgrade and the recovery of pipes