Rialp Pumping Station

Our staff has achieved the construction of the pumping room and the loading system by installing the main supply pipe of the Segarra-Garrigues canal.

The station is equiped with 8 pumps and pipes of 3000 mm of diameter. Our staff also completed all the formworks and built the station enclosure.

  • Location: Rialp (Lleida)
  • Construction company: UTE FCC-Comapa
  • Construction year: 2003
  • Execute items:

    9915.84 m3 of structural concrete poured

    15,408.82 m3 of concrete poured for the realization of cable channels

    10,919.47 m2 formwork of double-sided walls

    5177.03 m2 formwork of single-sided walls

    3062.64 m2 formwork of concrete manhole covers

    1922.41 ml. Installation of hydro-expansive joint

    23497.00 u.  Installation of DYWIDAG anchorages

    4092.93 m2 Laying and painting of PVC plates for walls waterproofing

    31,144.00 kg Renewal of reinforcement steel bars in the caisson area

    218.00 ml. of welding

    1277.42 m2 construction of 10 cm thick walls

    2061.52 m2 of walls face lifting

    1385.43 m2 Laying of terrazzo

    27488.00 u. Erection and dismantling of scaffolding

    2248.00 ml. Laying of drainage pipes including the laying of geotextile and a layer of gravel

    112.36 m2 formwork for Howell-Bunger valve installation